Project Schedule

Notice to Proceed on Project July 2, 2015
Hazardous Material Abatement/Demolition August - October 2015
Excavation/Shoring September – November 2015
Foundation work November 2015 – February 2016
Building construction begins February 2016
Structural framework completed September 2016
Interior Build-Out Construction July 2016 – May 2017
Landscaping March – June 2017
Punch List May – June 2017
Substantial Completion June 2017
Final Completion August 2017
Tenants Move In November 2017 – February 2018