Joel Pritchard Building
The Pritchard Rehabilitation and Expansion Project addresses the significant functional, health and life safety hazards of the Joel Pritchard Building (Pritchard) that were outlined in the 2017 State Capitol Development Study and earlier phases of the LCM Predesign study. Some issues included:
- More than 60 percent of the building was empty because it was built for book storage and could not be used as office space.
- The building’s proximity to a steep, unstable slope and its inadequate lateral resistance system increased the risk of failure during a seismic event.
Major impacts
At this time, all work on the Pritchard Rehabilitation and Expansion Project is taking place within construction fencing.
- 15th Avenue SW west of Water Street is closed through July 31.
- Assigned parking stalls behind John A. Cherberg (JAC) Building are closed through Dec. 31.
- EV charging stations and assigned parking stalls behind the John L. O’Brien (JLOB) Building are closed through Dec. 31.
- EV Charging stations behind John A. Cherberg (JAC) Building are closed through July 31.
Latest updates
Exterior
- Building exterior cladding and window installation is complete.
Interior
- Painting first floor.
Stay up to date
To stay up to date on the progress of the Joel Pritchard Building Rehabilitation and Expansion Project, subscribe to the LCM Weekly Update. LCM Weekly Update Oct. 7-11
Project schedule
April 2020 - March 2022: Preservation/Expansion Predesign and Validation study
April 2022 - February 2024: Programming and design
March 2024 - June 2024: Hazmat abatement and deconstruction
July 2024 - October 2024: Hillside stabilization
November 2024 - August 2026: Building construction
Substantial completion expected by end of July 2026
Public Involvement
The design underwent months of public input, including an environmental review and feedback from the LCM Landscape Peer Review Panel.