Joel Pritchard Building

Architectural rendering of the new Joel M. Pritchard Library
Architect renderings by DLR Group and HBB Landscape Architecture.

The Pritchard Rehabilitation and Expansion Project addresses the significant functional, health and life safety hazards of the Joel Pritchard Building (Pritchard) that were outlined in the 2017 State Capitol Development Study and earlier phases of the LCM Predesign study. Some issues included:

  • More than 60 percent of the building was empty because it was built for book storage and could not be used as office space.
  • The building’s proximity to a steep, unstable slope and its inadequate lateral resistance system increased the risk of failure during a seismic event.

Subscribe for weekly updates

Major impacts

At this time, all work on the Pritchard Rehabilitation and Expansion Project is taking place within construction fencing.

Before visiting campus, please note:

  • The construction site is fenced in, limiting some pedestrian routes and parking.
  • Expect increased noise, dust and construction traffic during work hour from 7:00 a.m. to 5:30 p.m.
  • The Pritchard, Cherberg and O'Brien parking lots are closed.
  • The sidewalk on the south side of 15th Avenue SW west of Water Street is closed.
  • The sidewalk on the west side of Water Street south of 15th Avenue SW is closed.

Latest updates

Exterior

Exterior cladding is added to the Pritchard Building with a lift machine.
  • Crews continue with filling and calking exterior concrete joints.

Windows

New windows have been added in the construction process of the Pritchard Building.
  • Crews have finished installing exterior window frames and windows on the second and third floors.

Interior

Sheets of drywall are being installed in the Pritchard Building.
  • Installation of interior drywall is well underway.

More construction photos.

Stay up to date

To stay up to date on the progress of the Joel Pritchard Building Rehabilitation and Expansion Project, subscribe to the LCM Weekly Update. LCM Weekly Update Oct. 7-11

View updated project photos.

Project schedule

April 2020 - March 2022: Preservation/Expansion Predesign and Validation study

April 2022 - February 2024: Programming and design

March 2024 - June 2024: Hazmat abatement and deconstruction

July 2024 - October 2024: Hillside stabilization

November 2024 - August 2026: Building construction

Substantial completion expected by end of July 2026

Public Involvement

The design underwent months of public input, including an environmental review and feedback from the LCM Landscape Peer Review Panel.

Related links