Joel Pritchard State Library

Architectural rendering of the new Joel M. Pritchard Library
Architect renderings by DLR Group and HBB Landscape Architecture.

The Pritchard Rehabilitation and Expansion Project addresses the significant functional, health and life safety hazards of the Joel Pritchard State Library (Pritchard) that were outlined in the 2017 State Capitol Development Study and earlier phases of the LCM Predesign study. Some issues included:

  • More than 60 percent of the building was empty because it was built for book storage and could not be used as office space.
  • The building’s proximity to a steep, unstable slope and its inadequate lateral resistance system increased the risk of failure during a seismic event.

Subscribe for weekly updates

Major impacts

A large crane will be on the Pritchard jobsite for approximately 12 months beginning on Nov. 1, 2024.

  • Crane stands approximately 188 feet high. 
  • No impacts outside of construction fencing are expected when crane is carrying construction loads.
  • While the crane is “resting,” otherwise known as free slewthing, there will be times when the mast rotates as the wind blows. There will be no load on the crane when this happens.
  • All industry standard safety measures are being followed while crane is on site.
  • No increase above normal construction noise is expected.
A conceptual rendering of a crane towering above the Pritchard Library construction site, with the Cherberg, Insurance, and Legislative Buildings to the south of the site.
Architect rendering of the construction crane.

Before visiting campus, please note:

  • The construction site is fenced in, limiting some pedestrian routes and parking.
  • Expect increased noise, dust and construction traffic during work hour from 7:00 a.m. to 5:30 p.m.
  • Pritchard parking lot is closed.

Stay up to date

To stay up to date on the progress of the Pritchard Rehabilitation and Expansion Project, subscribe to the LCM Weekly Update. LCM Weekly Update Oct. 7-11

View updated project photos.

Project schedule

April 2020 – March 2022 – Preservation/Expansion Predesign and Validation study

April 2022 – February 2024 – Programming and design

March 2024 - June 2024 – Hazmat abatement and deconstruction

July 2024 - October 2024 – Hillside stabilization

November 2024 – July 2026 – Building construction

Substantial completion expected by end of July 2026

Latest updates

  • Deconstruction and abatement are complete.
  • Hillside stabilization is underway

Public Involvement

The design underwent months of public input, including an environmental review and feedback from the LCM Landscape Peer Review Panel.