Joel Pritchard Building

Architectural rendering of the new Joel M. Pritchard Library
Architect renderings by DLR Group and HBB Landscape Architecture.

The Pritchard Rehabilitation and Expansion Project addresses the significant functional, health and life safety hazards of the Joel Pritchard Building (Pritchard) that were outlined in the 2017 State Capitol Development Study and earlier phases of the LCM Predesign study. Some issues included:

  • More than 60 percent of the building was empty because it was built for book storage and could not be used as office space.
  • The building’s proximity to a steep, unstable slope and its inadequate lateral resistance system increased the risk of failure during a seismic event.

Subscribe for weekly updates

Major impacts

A large crane is located on the Joel Pritchard Building jobsite and will remain there until early 2026.

  • No impacts outside of construction fencing are expected when crane is carrying construction loads.
  • No increase above normal construction noise is expected.

Before visiting campus, please note:

  • The construction site is fenced in, limiting some pedestrian routes and parking.
  • Expect increased noise, dust and construction traffic during work hour from 7:00 a.m. to 5:30 p.m.
  • The Pritchard, Cherberg and O'Brien parking lots are closed.
  • Assigned parking stalls along 15th Avenue SW west of Water Street are closed through November.
  • 15th Avenue SW west of Water Street is closed through November.
  • The sidewalk on the south side of 15th Avenue SW west of Water Street is closed.
  • The sidewalk on the west side of Water Street south of 15th Avenue SW is closed.

Latest updates

The last beam of the Pritchard Building project is hoisted by a crane with a fir tree and an American flag resting on it.
Last beam being hoisted to the roof area

The construction team recently celebrated a major project milestone with a Topping Out ceremony when the last structural beam was placed signifying the end of the structural phase of the project.

The Pritchard Building project as of July 8, 2025.  The building's skeletal structure is showing and a user can see through the structure frame of exposed beams.
July 8, 2025

More construction photos.

Stay up to date

To stay up to date on the progress of the Joel Pritchard Building Rehabilitation and Expansion Project, subscribe to the LCM Weekly Update. LCM Weekly Update Oct. 7-11

View updated project photos.

Project schedule

April 2020 - March 2022: Preservation/Expansion Predesign and Validation study

April 2022 - February 2024: Programming and design

March 2024 - June 2024: Hazmat abatement and deconstruction

July 2024 - October 2024: Hillside stabilization

November 2024 - July 2026: Building construction

Substantial completion expected by end of July 2026

Public Involvement

The design underwent months of public input, including an environmental review and feedback from the LCM Landscape Peer Review Panel.

Related links